DECEMBER
Dec. 19th- Looked at Property
Dec. 20th – Initial Environmental Research
Dec. 26th – Meet with the bank
Dec. 28th – Offer to Purchase submitted
Dec. 29th – Notification of Alder and Neighborhood
JANUARY
Jan. 2nd – Offer to Purchase Accepted
Jan. 2nd – Meet with small group of neighbors for initial feedback
Jan 8th – Meet with Zoning and Public Health Department
Jan. 8th – Neighborhood Association Meeting
Jan. 13th – Meet with Landscaper, Architect and Construction Company at the site
Jan. 13th – Meet with James Reeb Peace, Justice and Sustainability Committee
Jan. 15th – Alder Neighborhood Meeting
Jan. 17th – Meeting regarding fence, art, landscaping
Jan. 23rd – Neighborhood Plan Steering Committee – Emerson East/Eken Park/Yahara
Jan. 24th – 2nd meeting on fence, art, landscaping
Jan. 25th – Sustainable Saturday presentation
Jan. 27th – Obtain info from engineering staff on flooding and environmental concerns
Jan. 27th – Schools confirm they don’t have an official position, its up to the neighborhood
Jan. 27th – Meeting with UDC and Planning Staff
Jan. 29th – Meeting with the Police Department
Jan. 29th – UDC application for Inormational presentation
Jan. 30th – Meeting with Fire Department
FEBRUARY
Feb 5th – Informational presentation to Urban Design Commission
Feb. 5th – Earliest Date for Application Submittal (UDC – April 2nd , Plan Commission April 7th , Council April 29th)
Feb 5th –
Scheduling:
2nd neighborhood meeting with Alder Palm
Meeting with immediate neighbors and Alder Palm
MARCH
March 5th –
APRIL
April 2nd – Urban Design Commission
April 7th – Plan Commission
April 29th – Council Approval
MAY
May – Move workshop and houses
May 31st – lease is up in current location (4235 Argosy Ct)
JUNE
Improvements made to property to meet campground regulations
only three houses parked on the property that are being lived in.
JULY
Obtain campground permit